| Phase I: |
-- |
Jetty Jack Removal and Treatment at 2003 Burn Sites (I-40 and Montano) - COMPLETE |
|
| Phase II: |
-- |
Levee Road Repair (South Diversion Channel to I-25 east side) - COMPLETE |
|
| Phase III: |
-- |
Installation of Emergency Access bridges across Riverside Drain to Bosque (Gabaldon, Arenal, Louise) - COMPLETE |
|
| Phase IV: |
-- |
Fuel Reduction, exotic removal, jetty jack removal, debris removal, and revegetation at various locations in Albuquerque and Corrales. November 1, 2004 - March 31, 2005 |
|
| Phase V: |
-- |
Installation of Emergency Access bridges across Riversite Drain to bosque (I-25, Clark, Atrisco, Dixon Rd., Corrales, Sandia Pueblo);
Levee Road Repair (Central - I-25, west side; Bridge - South Diversion Channel, east side); Installation of dry hydrants (Corrales) March 1, 2005 - September 1, 2005 |
|
| Phase VI: |
-- |
Fuel Reduction, exotic removal, jetty jack removal, debris removal, and revegetation at various locations in Albuquerque, Corrales and Sandia Pueblo. September 1, 2005 - March 31, 2006 |
|
 |